The customer signed for one thing and the job turned into another. They want an extra bathroom done, you opened a wall and found rot, or the foam they approved has to change. A change order captures that, gets their signature on it, and bills it — without touching the contract they already signed.
The one thing to understand
A change order is the CHANGE, not the new job. You enter what's being added or taken away, and BidTorch adds it to the signed contract. On a $10,000 job, a change order for $2,000 of extra work makes the job $12,000 — you do NOT retype $12,000.
Tip
While you build one, the summary panel shows "base + this change = revised total" so you can see exactly what the job becomes before you send it. If that number looks wrong, you've entered the new total instead of the change.
Raising one
- 1Open the job and click + Change order under Change orders. (On an accepted quote that hasn't been converted yet, the same button is on the quote — it follows onto the job when you convert.)
- 2Give it a title the customer will understand: "Add second-floor bathroom", not "CO-2".
- 3Add a line per item of changed work — + From catalog pulls a priced service or material straight from your price book, + Add line types one in — with cost and price just like a quote line. The margin badge and below-cost warning work here too.
- 4Check the revised total, then Send to customer.
- 5They open the link, review it, and approve with a signature — the same way they accepted the quote.
Nothing moves until they approve. A draft or sent change order doesn't touch the job total, so you can price options without committing.
The three shapes
- ADDING WORK — one or more lines at normal prices. A $2,000 change order on a $10,000 job makes it $12,000.
- CREDITING WORK — enter a NEGATIVE price. Dropping $800 of scope makes a $10,000 job $9,200.
- SWAPPING A PRODUCT — two lines in one change order: credit what they approved, add the replacement. Deduct closed-cell foam at −$4,425, add open-cell at $2,175, and the job drops by $2,250.
Tip
For a swap, always show both lines rather than one net figure. The customer approved the original product — seeing it credited in full, then the replacement charged, is what makes the new number obvious instead of looking like a random discount.
Getting paid for it
Approved change orders are added to the job's total automatically, so "Remaining" always reflects what the customer actually owes. When you invoice the remaining balance, each approved change order comes across as its own labelled line — so the customer sees the original work and every amendment itemised on one document.
- Progress invoices (stage percentages) are a percentage of the ORIGINAL contract, not the amended one — "40% at rough-in" means what it meant when they signed.
- Change-order money is billed as its own lines, so it's never quietly folded into a stage.
- Each change order can only be billed once — once it's on an invoice it's locked, unless you void that invoice.
Fixing a mistake
Before it's billed, reopen a change order to edit it, or delete it outright — the job total follows along either way. Once it's on an invoice it's frozen, because changing it then would leave the invoice charging one number while the job says another. From that point on, adjust the work with a NEW change order — credit the old amount and add the corrected one — so the paperwork and the money stay in step.
Voiding the invoice unlocks it again. A voided invoice charges nothing, so its change orders go back to un-billed and you can edit them or put them on a different invoice. The one thing you can't do is delete a change order while a voided invoice still lists it — delete that invoice first if you want it gone for good.
Tip
If you void an invoice and then bill one of its change orders somewhere else, you can no longer Restore the original — BidTorch will tell you which change order is in the way. That's on purpose: restoring it would charge the same amendment on two invoices. Void the newer invoice first, or just leave the old one voided and bill what's left on a fresh one.